Diversions in place until August
Revised plans for a major roadworks scheme in the north of the Island will mean less disruption to road users - according to the Infrastructure Minister.
A project to resurface part of Lezayre Road, and create provision for a connection to a new water main, started this week.
Work on the stretch of road had been planned for last year, but was put on hold following concerns over the length of time a full reconstruction would take.
Ray Harmer says revised working hours will help to further shorten the length of the disruption:
Pedestrian access is being maintained throughout the works, but motorists are being diverted onto the Jurby Road between Sulby Bridge and Parliament Square.

Amber weather warning issued as strong winds and coastal conditions expected overnight
Hospice funding criticised by UK charity chief amid Isle of Man service cuts
Sailings cancelled as storm brings gale-force winds
Manx Mountain Marathon route diverted over safety concerns amid forecast strong winds
Rushen MHKs to meet with Southern Group Practice over appointment concerns