20 week project sees bridge from 1938 replaced
Work on the new harbour bridge in Peel has been completed ahead of schedule, according to the Department of Infrastructure.
Following construction which began in October, the bridge is now fully accessible to both traffic and pedestrians.
Just over £400,000 was invested by the department to replace the 80-year-old timber structure which had reached the end of its usable life.
It now features a concrete deck and steel beams.
Taking to twitter, the DoI thanked the community for its patience.
Peel’s new harbour bridge opened to traffic today around 2 weeks ahead of schedule. It features a concrete deck on steel beams and replaces the timber bridge, built in 1938. The team thanks the community for its patience while the project has taken place. #isleofman @PeelOnline pic.twitter.com/QerEwgmyu1
— IOM Infrastructure (@iominfra) March 7, 2019


Person suffers 'significant injuries' in 'serious assault' near Peel
Business case for horse trams to be put before Tynwald in July
Plans to turn 'underused space' in central Douglas into wellness retreat
Employment grievance 'upheld' against board of Peel Commissioners
2026 Parish Walk takes place today