Auldyn Construction struggling to resource Douglas scheme
Douglas promenade work has been delayed because the contractor is struggling for resource.
Auldyn Construction has moved the expected completion date to the end of September – it should have been finished in August.
The Department of Infrastructure will now step in to carry out parts of the project.
Speaking on Manx Radio Breakfast Minister Tim Baker says the delay is down to a lack of workers: